This guide provides essential information on the permits required for property transactions and developments in Indonesia. It covers the necessary documents, approval processes, and regional regulations to ensure your project complies with local laws. Stay informed and navigate the permitting process with ease for a smoother investment experience.

Environmental Permit Requirements

AMDAL Required for:

  • Buildings ≥ 10,000 m²
    Warehousing area ≥ 10,000 m²
  • Residential area ≥ 25 hectares
  • Apartments/hotels ≥ 10,000 m²
  • Shopping centers ≥ 10,000 m²

UKL-UPL Required for:

  • Buildings 5,000 – 10,000 m²
  • Warehousing 5,000 – 10,000 m²
  • Residential area 5 – 25 hectares
  • Apartments/hotels 5,000 – 10,000 m²
  • Shopping centers 5,000 – 10,000 m²
  • KKPR Application
  • Environmental Permit
  • PBG Application
  • Construction Commencement
  • Building Worthiness Certificate (SLF)

KKPR: 7-14 working days
Environmental Permit:

  • SPPL: 14 days
  • UKL-UPL: 3-6 Months max
  • AMDAL: 6 – 12 Monts Max
  • PBG: 14-30 working days

Ensure a smooth property transaction by understanding regional variations, seeking professional assistance, and maintaining thorough documentation. Stay compliant with local regulations, conduct regular inspections, and adhere to safety standards. Act now: Consult with experts and stay organized to secure a successful investment.

TITLE TYPES

Understand the legal and practical differences in ownership types before deciding

BUYING GUIDE

Understand every stage of purchasing your property with confidence and clarity

TAX GUIDE

Your guide to the legal and tax framework for property transactions.

Compare listings

Compare